The Hidden Factory: How Much More Can Your Existing Machines Actually Produce?
Before you buy another machine, find out what your factory can already produce
A quote for a new machine is usually a rather persuasive piece of documentation. It comes with a price, a delivery date and a photograph of something shiny; sometimes there is even a financing proposal attached, along with a salesperson willing to explain how this particular investment will transform your production capacity.
What it rarely comes with, however, is an honest assessment of how much production capacity you already own, pay for every month, and somehow manage not to use.
Before approving another machine, I would want answers to three fairly straightforward questions: how much good product can the existing equipment actually produce, where exactly are we losing production time, and how much of that lost time could we realistically recover?
Only then does it make sense to compare the cost of recovering existing capacity with the cost of buying more.
This is where Overall Equipment Effectiveness (OEE) comes into the picture.
Not as another percentage to display on a dashboard during management meetings, but as a way of understanding where production capacity disappears between the theoretical capabilities of a machine and the products that actually leave the factory.
In many factories, there is effectively a second factory hiding inside the first one.
It consists of production minutes that have already been paid for, along with the machines, operators, floor space, electricity and maintenance needed to run them, yet somehow those resources are not being converted into saleable output.
The interesting part is that this hidden capacity is not necessarily sitting in one obvious place.
Some of it disappears through unplanned downtime, some through frequent changeovers, minor stops, reduced operating speeds or quality problems that force otherwise perfectly good production time to be spent making products that cannot be sold. Individually, these losses may look insignificant; accumulated across shifts, machines and an entire year, they can represent a rather expensive habit.
The exercise is therefore not simply to calculate an OEE score, put it on a screen and congratulate ourselves for having introduced another KPI.
It is to identify where those minutes are going, understand the operational reasons behind the losses, put a financial value on the recoverable capacity and establish which improvements actually make economic sense.
And sometimes, after doing all that, the conclusion will still be that another machine is necessary.
There is nothing wrong with buying machinery; I have been involved in enough investment and operational decisions to appreciate that capital expenditure is sometimes precisely what a business needs.
I would simply prefer to see a business buy a machine because it needs additional capacity, rather than because nobody has bothered to check how much of the capacity it already owns is sitting idle.
The salesperson may not be particularly enthusiastic about that distinction, but the balance sheet usually is.
What is Overall Equipment Effectiveness, and what does it tell you about production?
Overall Equipment Effectiveness measures how effectively a machine or production line converts its planned production time into good output at its ideal operating speed.
It combines three factors:
Availability: did the machine run when it was supposed to? Run time divided by planned production time.
Performance: did it run at its ideal speed while operating? Ideal cycle time multiplied by total output, divided by run time.
Quality: did it produce acceptable parts? Good output divided by total output.
Multiply the three ratios to get the overall result.
A useful shortcut is:
Good parts × Ideal cycle time ÷ Planned production time
OEE measures the proportion of planned production time that is genuinely productive, meaning time spent manufacturing good parts at the ideal production rate.
In other words, it connects three things that are often discussed separately in factory management: whether the machine was running, how fast it was running, and whether what it produced was actually fit for sale.
The methodology emerged from Japan’s Total Productive Maintenance (TPM) movement, with Nakajima Seiichi widely credited with developing and popularising the OEE framework.
The familiar Six Big Losses are grouped under its three components: equipment breakdowns and setup or adjustment losses affect availability; minor stops and reduced operating speed affect performance; while process defects and reduced yield during start-up affect quality (OEE factors).
That is the methodology.
What matters to a business, however, is not whether someone can calculate the percentage correctly, but what the numbers reveal about the operation and, more importantly, what management can do about it.
A machine can have excellent availability while consistently producing below its designed speed; another can run at an impressive rate but generate so many rejects that a significant proportion of its output never becomes saleable product.
A third may lose hours to changeovers, while an apparently healthy machine spends a considerable part of every shift waiting for materials, instructions or an operator.
All situations can produce disappointing OEE figures, but they represent different operational failures, with different financial consequences and, naturally, different solutions.
In my experience this is also where OEE is frequently misunderstood by SME c-level managers.
It is not a performance grade for individual operators, a comprehensive measure of factory productivity or a direct indicator of profitability.
Nor does a higher score automatically mean that the business is producing more of what its customers actually want to buy.
A peer-reviewed analysis of OEE and equipment effectiveness examines the relationship between equipment utilisation and the reliability of comparisons, while a separate paper on common OEE misconceptions highlights problems such as overlooking financial implications and pursuing so-called world-class scores without establishing whether they create business value.
My interpretation is rather simple: a machine can improve its OEE score without the business shipping a single additional order.
If that machine is not the bottleneck restricting the factory’s output, improving its performance may achieve very little commercially; you have made one part of the operation more efficient without necessarily improving the performance of the system as a whole.
This is the distinction between tactically optimising equipment and strategically optimising a business.
The former can produce impressive dashboards, while the latter should produce more saleable output, lower unit costs, shorter lead times or some combination of the three.
And it becomes a rather important distinction when someone asks you to approve a six-figure investment in additional machinery.
Before spending the money, it is worth establishing whether you actually have a capacity problem, or simply a problem with using the capacity you have already purchased.
How do you calculate Overall Equipment Effectiveness? A worked production shift
Let’s use a hypothetical manufacturer.
One machine operates an eight-hour shift:
Shift length: 480 minutes.
Breaks: 30 minutes.
Planned production time: 450 minutes.
During the shift:
A breakdown takes 25 minutes.
A changeover takes 35 minutes, including 12 minutes spent looking for a fixture.
The machine waits 20 minutes for material.
That gives us 80 minutes of stoppages and 370 minutes of actual running time.
The machine produces 600 parts. Thirty are rejected, eleven of them in the ten minutes following the changeover. The ideal cycle time is 30 seconds per part.
Now the calculation:
Measure | Calculation | Result |
|---|---|---|
Availability | 370 ÷ 450 | 82.2% |
Performance | (600 × 0.5) ÷ 370 | 81.1% |
Quality | 570 ÷ 600 | 95.0% |
Overall result | 82.2% × 81.1% × 95.0% | 63.3% |
The shortcut produces the same result:
570 good parts × 0.5 minutes = 285 minutes of fully productive time.
285 ÷ 450 = 63.3%.
In plain language, the machine was scheduled to produce for 450 minutes.
Only 285 of those minutes were converted into good parts at ideal speed.
The remaining 165 minutes were lost:
80 minutes to stoppages.
70 minutes to running below ideal speed.
15 minutes to rejected parts.
That is the second factory: 165 minutes of production potential that disappeared during one shift.
It does not mean that all 165 minutes can be recovered.
Some losses may be unavoidable, some may be too expensive to eliminate, and some may not affect the factory’s actual output at all.
But now we have something more useful than an opinion that the machine is too slow.
We have a list of losses that can be investigated and priced.
Why can the same machine have three different efficiency scores?
Before building a business case around 63.3%, change the definitions and see what happens.
Scenario | Availability | Performance | Quality | Result |
|---|---|---|---|---|
A: all stops count, ideal cycle 30 seconds | 82.2% | 81.1% | 95.0% | 63.3% |
B: changeover excluded from planned time | 89.2% | 81.1% | 95.0% | 68.7% |
C: ideal cycle changed to 36 seconds | 82.2% | 97.3% | 95.0% | 76.0% |
Same machine, same shift, same parts. Three scores almost thirteen percentage points apart.
All three are mathematically correct according to their respective definitions; that does not make them equally useful for managing production.
Scenario C is particularly interesting; by setting the ideal cycle time to 36 seconds instead of 30, the machine suddenly appears to run at 97.3% performance.
The slow running has largely disappeared from the calculation.
The calculation guidance warns that performance above 100% can indicate that the ideal cycle time has been set too high.
But a number below 100% does not automatically mean the underlying assumption is correct.
Before collecting data, agree on three definitions:
Planned production time. Shift length minus breaks. Decide whether changeovers and planned maintenance count as losses or are excluded from planned time. Either approach can be defended, but the definition must remain consistent.
Ideal cycle time. The fastest sustainable cycle under optimal conditions, not the average speed the machine happens to achieve. Record the source, date and person who agreed it.
What counts as a stop. Define the minimum duration of a stoppage. My suggested threshold is two minutes, not an industry standard. Shorter pauses can be tallied as micro-stops and reflected in performance. Longer stoppages should receive a reason code.
If you inherit an efficiency score from a previous manager, ask who defined the ideal cycle time and how it was established.
So, if nobody knows, the number is difficult to compare with anything, including last month’s number.
Does planned downtime count against production efficiency?
There is no universal agreement in the sources.
The OEE reference site includes planned stops such as changeovers in stop time, meaning they count against availability.
A guide from TeepTrak describes planned downtime as usually excluded, to focus on avoidable losses.
Take the 35-minute changeover in our example; twelve minutes were spent looking for a fixture.
Under one definition, the entire changeover is a loss… under another, it is excluded from planned production time.
The score changes, but the factory has not suddenly become more productive.
Always ask for the methodology when reviewing those shiny data points…
For an exercise intended to identify recoverable capacity, I would count changeovers as losses.
They are often precisely the kind of operational activity that can be improved through better preparation, tooling, standard work and SMED (Single-Minute Exchange of Die) principles.
A definition that excludes a loss from the calculation does not make that loss disappear from the production schedule.
There is a practical distinction here, the purpose of the measurement matters.
If you are comparing equipment against a particular reporting standard, follow that standard.
If you are trying to find additional production capacity, make sure the measurement exposes the losses you might actually be able to recover.
Is 85% a good production efficiency score, or is it misleading?
There is one number that keeps appearing in discussions about manufacturing efficiency 85%, no less.
Apparently, if your factory falls below it, a man in a black suit and a white hard hat will descend from the upper floors of the office building to ask whether you have a minute… and you really don’t want that, do you?
It is commonly presented as the world-class benchmark… so naturally, that is exactly what your boss will find when he visits the website of the equipment manufacturer whose machine he has just bought.
The figure comes from multiplying three commonly quoted benchmarks:
90% availability.
95% performance.
99% quality.
The result is 84.6%, usually rounded to 85%.
The reference site associates this benchmark with Nakajima’s practical experience and also cautions against treating it as a universal target.
It describes a particular historical manufacturing context, not a law of physics that applies equally to every factory.
A high-volume production line running a stable product is not the same operation as a small manufacturer changing tooling and product specifications several times per shift.
A business producing a wide variety of low-volume components may have a perfectly rational reason for operating differently from a factory producing millions of identical parts.
My view is that 85% is a useful reference point, not a management objective in its own right.
A better question is whether the machine that limits your output is improving against consistent definitions, and whether that improvement creates additional saleable production at an acceptable cost.
If your management meeting spends more time debating why the score is 78% rather than 85% than discussing the reasons for lost production, the metric has become the problem.
OEE versus TEEP: how much capacity are you not scheduling?
So far, we have only considered time during which the machine was scheduled to produce.
But a factory does not operate every minute of every day.
A machine might work one eight-hour shift, five days a week. That leaves a substantial amount of calendar time during which it is not scheduled to run.
This is where Total Effective Equipment Performance (TEEP) becomes useful.
TEEP combines equipment effectiveness with utilisation:
TEEP = OEE × Utilisation
And:
Utilisation = Planned Production Time ÷ Total Available Calendar Time
The distinction is important.
The first calculation tells you how effectively the machine operates when production is scheduled.
The second tells you how effectively the business uses the machine across all available time.
Return to our example.
One eight-hour shift, five days a week, gives us 2,250 planned production minutes.
There are 10,080 minutes in a seven-day week.
Utilisation is therefore:
2,250 ÷ 10,080 = 22.3%.
Multiply that by the 63.3% effectiveness score:
TEEP = 14.1%.
In other words, only around 14.1% of the machine’s total calendar time is converted into good production at ideal speed.
There are 7,830 minutes every week during which the machine is not scheduled to produce anything.
Some of that time may be economically justified.
There might not be enough orders, operators, materials or demand to justify another shift.
But if demand exists, the business has another potential source of capacity.
It could introduce another shift, extend operating hours or reorganise production planning.
Of course, none of these options is free.
People need to be employed, materials need to be available, maintenance needs to be scheduled and customer orders need to justify the additional production.
The important point is that there is a difference between losing time during a scheduled shift and simply not scheduling the machine for more hours.
A factory can have a machine with poor effectiveness during its existing shift. It can also have a machine that performs reasonably well but is used for only a small part of the available calendar.
Those are different management problems.
The OEE glossary explains the relationship between these measurements. The commercial question is what additional operating time would actually be worth to your business.
Should you buy another machine, introduce another shift or improve the existing process?
At this point, we can return to the original purchase decision.
You believe you need more production capacity.
There are three broad ways to obtain it:
Buy capacity.
Purchase another machine. This comes with the equipment price, installation, floor space, power, tooling, training, maintenance, financing and potentially additional working capital.
It may be the right answer, particularly if the existing equipment cannot perform the required operation or confirmed demand exceeds what the factory can produce.
Schedule more capacity.
Introduce another shift, extend operating hours or use the existing equipment for a greater proportion of the available calendar.
This requires labour, supervision, maintenance coverage, materials and a production schedule that supports extended operations.
A machine that is idle for sixteen hours a day may look like an obvious opportunity. But if the business cannot recruit operators, supply materials or sell the additional output, those hours are not commercially available capacity.
Recover existing capacity.
Reduce stoppages, improve changeovers, eliminate waiting, address quality problems and remove unnecessary movement or process delays.
This is where Lean Manufacturing principles become practical rather than decorative.
The usual subjects are worth discussing with production and line managers: waste (muda), bottlenecks, changeover times, material flow, unnecessary movement, waiting, work in progress and standard work.
In our example, the machine loses 35 minutes to a changeover, including 12 minutes looking for a fixture, and another 20 minutes waiting for material.
These are not necessarily equipment problems.
The fixture needs a defined location and the changeover needs better preparation. Material needs to arrive when production requires it.
Neither problem is solved by buying another machine.
Only the first option comes with a glossy brochure. The other two come with a spreadsheet and some uncomfortable conversations.
How much additional production could you recover without buying another machine?
Let’s return to the invented shift.
Suppose the factory takes two actions:
It reduces the 35-minute changeover to 15 minutes by preparing tooling and fixtures in advance.
It eliminates the 20-minute wait for material through better production planning and material handling.
That recovers 40 minutes of machine time.
The machine previously produced 600 parts in 370 minutes of running time.
At the same observed rate, another 40 minutes could produce approximately 65 additional parts.
At 95% quality, that is roughly 62 additional good parts.
The result is about 11% more good output from the same machine, the same shift and the same factory space.
The figures are invented. The method is the point.
And this is where the business case becomes more interesting than the efficiency score.
If recovering those 40 minutes allows the business to fulfil additional orders without buying another machine, the value can be substantial.
But there is an important qualification: this only increases factory throughput if the machine is actually limiting the production system.
If the next process cannot accept additional output, the recovered capacity may simply create more work in progress. If the machine is waiting for another bottleneck, improving its performance will not increase the number of finished products shipped.
This is why I would not start an improvement programme by looking for the machine with the lowest score.
I would start by identifying the constraint that limits the factory’s output.
Then I would investigate what prevents that constraint from producing more.
How do you calculate whether recovering capacity is worth the investment?
Start with the commercial value of additional production.
You need to establish:
How many additional good units could realistically be produced?
Is there confirmed demand for them?
What is the contribution margin per additional unit?
What additional labour, energy, materials, maintenance and other variable costs are required?
What will the improvement cost to implement and maintain?
For a simplified calculation:
Annual benefit = Additional saleable units × Contribution margin per unit
Then compare that benefit with the cost of recovering the capacity.
The same logic applies to purchasing another machine. Its purchase price is only one part of the investment. Installation, tooling, training, maintenance, energy, floor space, financing and the additional operating costs all belong in the calculation.
You should compare the options on the same basis:
Option | What to include in the business case |
|---|---|
Improve existing process | Engineering time, tooling, training, process changes and ongoing costs |
Introduce another shift | Wages, supervision, maintenance coverage, utilities and additional operating costs |
Buy another machine | Purchase, installation, tooling, financing, space, training and lifecycle costs |
Do not assume that every recovered minute becomes additional revenue. It only has financial value if the business can use it to produce something it can sell, or if it avoids a cost it would otherwise incur.
A machine producing more parts that nobody has ordered is not a particularly impressive investment.
Are you improving the bottleneck, or just making a dashboard look better?
This deserves its own discussion because it is one of the easiest ways to waste money on operational improvement.
Imagine a production line with three stages:
Cutting.
Machining.
Assembly.
If machining is the constraint, improving cutting efficiency may simply create a larger queue of work in progress before machining.
If assembly is the constraint, increasing machining output may only fill the warehouse with unfinished products.
A machine can improve its efficiency score while total factory throughput remains unchanged.
This is why production performance needs to be considered as a system.
Look at the actual flow of material, the queues between processes, the time orders spend waiting, and the number of finished products shipped.
Identify where work accumulates and where the production system is unable to keep up.
The machine with the worst score is not automatically the best investment opportunity.
A better score on a machine that sits waiting for the bottleneck produces a nicer chart and the same invoices.
The same principle applies to technology investments.
If breakdowns dominate the losses, predictive maintenance may be worth investigating.
I discuss the wider business case in The End of Guesswork: Why Predictive Maintenance Is the Cornerstone of the Manufacturing Future.
If waiting and manual re-keying dominate, the solution may involve production planning, information flow or better integration between systems.
My ERP migration case study illustrates why mapping the process should come before choosing the software.
The same investment principle applies to automation more broadly: understand the loss first, improve the process where possible, and only then decide whether technology is the economical solution.
I explored that in Business Automation 101: So, How Much for That?.
Do you need production monitoring software, or will an Excel spreadsheet do?
You do not necessarily need to buy a monitoring platform to begin measuring production.
A clipboard, a spreadsheet and a reasonably disciplined process can provide enough information to identify the largest losses on one machine.
But manual measurement has a cost too.
Someone needs to record stoppages, count output, classify reasons and keep the information consistent.
Short stops are easily missed, and operators have other things to do than maintain a perfect spreadsheet while production is running.
Published prices give us a useful starting point.
At the time of checking on 14 November 2026:
I am not endorsing anyone besides prices and commercial terms change, so check the suppliers’ current offers before making a decision.
BUT… IMHO the choice between manual tracking and software is less ideological than either side might like.
A spreadsheet has a low cash cost but consumes people’s time and depends on consistent recording.
Sensors can capture machine states automatically, but they do not automatically understand why a machine stopped or whether the stop matters commercially.
A monitoring platform records the definitions somebody configured.
Five sensors installed on the wrong machines can produce a very precise answer to the wrong question.
My approach would be:
If you already know which machine limits output and what losses you want to investigate, a monitoring tool may be worthwhile.
If you do not yet know where the constraint is, begin with a short measurement exercise. Establish what needs to be measured before purchasing software.
If manual recording is too burdensome or the operation has many machines, consider a sensor on the most commercially important constraint rather than instrumenting the entire factory immediately.
The objective is not to own another dashboard. It is to make a better operational and investment decision.
When should you buy another machine anyway?
There are, of course, situations in which buying another machine is exactly the right decision; this is not an argument for squeezing another five per cent out of a twenty-year-old production line while customers wait six weeks for their orders.
There is a point at which operational improvements stop being an alternative to investment and become a distraction from the fact that the business simply needs more equipment.
If confirmed demand exceeds the maximum realistic output of the existing machinery, even after accounting for all available shifts, operating hours and achievable production rates, no amount of process optimisation will close the capacity gap.
The same applies when existing equipment cannot perform the required operation, meet the necessary tolerances or manufacture a new product to the required specification.
In those circumstances, OEE is useful for understanding what you already have, but it will not manufacture a capability that does not exist.
Another case is redundancy.
When a single machine represents a critical point of failure, purchasing a second one may have very little to do with increasing production capacity and everything to do with protecting business continuity.
If the failure of one piece of equipment can stop the entire production process, delay customer deliveries and put contractual commitments at risk, the investment should be evaluated against the potential cost of interruption, not simply against the additional units it might produce.
You are effectively buying insurance, although unlike most insurance policies, this one takes up several hundred square metres of factory floor.
Timing also matters, particularly when machinery has a delivery lead time of six months or more.
If procurement takes that long, postponing the entire investment decision until four weeks of production measurements have been completed may be counterproductive.
Start measuring while the procurement process is underway; the additional information may help determine the correct machine specification, production rate and number of units required, potentially avoiding an unnecessarily expensive purchase without losing valuable time.
The same applies to manufacturers operating high-mix, low-volume production, where frequent product changes, different batch sizes and varying process requirements can make a single factory-wide OEE figure rather misleading.
Rather than forcing the entire operation into one number, analyse individual product families, changeover times, throughput and the constraints affecting each production route.
A factory producing ten different products does not necessarily have ten equally demanding production processes, and treating them as if it did is unlikely to produce particularly useful investment decisions.
There is also a practical consideration that tends to disappear from theoretical discussions: measurement itself requires resources.
A small manufacturer may not have an industrial engineer, production analyst or spare operations manager available to record every stop, classify every loss and maintain a detailed production log.
If the measurement process becomes another administrative burden that nobody has time to own, it will eventually be abandoned, usually shortly after the person responsible discovers that they have been promoted to doing three other jobs.
In such cases, starting with a simple machine counter, inexpensive sensor or basic data collection system on the equipment that actually constrains production may be a far more sensible approach.
The objective is not to postpone capital expenditure indefinitely, nor to turn every machinery purchase into a six-month consulting exercise.
It is to establish whether the business has a genuine shortage of production capacity, a problem with using the capacity it already owns, or a combination of both.
Those situations require different investments, different operational decisions and, quite often, very different amounts of money.
A new machine may well be the answer. It is simply worth establishing the question before signing the purchase order.
How to assess your existing production capacity in four weeks
You do not need to start with a factory-wide transformation programme.
Start with one machine: preferably the one that limits what the factory ships.
One machine, one page, four weeks.
Before the first shift:
Select the machine that constrains factory throughput.
Agree and record planned production time.
Establish the ideal cycle time and document its source.
Agree what counts as a stop and the minimum stop duration.
Make sure production and management use the same definitions.
During each shift, record:
Breaks and planned non-production time.
Every significant stoppage, with start time, end time and one reason code.
A tally of micro-stops.
Total output.
Rejected parts and the reason for rejection.
Any unusual circumstances affecting production.
Use no more than seven initial reason codes:
Breakdown.
Changeover.
Adjustment.
Waiting for material.
Waiting for people.
Quality hold.
Other.
If ‘Other’ accounts for more than 10% of stoppage minutes, split it into more specific categories. That 10% is my suggested rule of thumb, not an industry standard.
Every Friday:
Calculate availability, performance and quality using the agreed definitions.
Rank stoppages by the total time lost.
Identify recurring reasons rather than isolated incidents.
Check whether the losses occur on the machine that constrains factory output.
Do not change definitions halfway through the month. Do not introduce an arbitrary target in the first month. And do not use the numbers to rank individual operators.
The purpose is to understand the process, not to find someone to blame.
At the end of four weeks, you should have a much clearer picture of what the machine does, where its time goes and which losses deserve further investigation.
You can then estimate the potential additional output, investigate the cost of recovering it and compare that with the investment required for another machine or shift.
That is a much more useful conversation to have before approving capital expenditure.
The example at a glance: what was hiding in one production shift?
Figure | Result |
|---|---|
Planned production time | 450 min |
Fully productive time | 285 min |
Lost to stoppages | 80 min |
Lost to slow running | 70 min |
Lost to rejects | 15 min |
Score, depending on definitions | 63.3% / 68.7% / 76.0% |
Utilisation, one shift, five days | 22.3% |
TEEP | 14.1% |
Potential time recovered in the example | 40 min |
Estimated additional good output | About 62 parts |
Before buying another machine, find the factory you already own
The arithmetic is relatively straightforward; establishing whether the numbers actually describe what is happening on the factory floor is considerably more difficult.
You need reliable production data, consistent definitions of downtime, speed losses and rejects, and enough operational understanding to distinguish between a genuine capacity constraint and a problem that happens to look like one in a spreadsheet.
An 85% OEE benchmark will not tell you whether to buy another machine, just as a dashboard displaying twenty-seven production indicators will not necessarily tell you which problem is costing the business the most money.
Improving a machine’s score is not the same as increasing factory output, and increasing factory output is not necessarily the same as producing more of what customers are willing to pay for.
The commercial question is therefore not how close you can get to some industry benchmark, but how much additional saleable output you can generate from the resources already available, what it would cost to achieve it, and how that compares with the cost and expected return of additional capacity.
Depending on the operation, the answer may involve better maintenance planning, shorter changeovers, improved material availability, a different production schedule or simply making better use of existing shifts.
It may mean introducing another shift before purchasing another production line, or investing in automation where repetitive manual operations are limiting throughput.
And sometimes, after examining all those options, the sensible decision is to buy another machine.
What matters is the sequence: understand the operation, identify the constraint, quantify the losses, evaluate the available improvements and only then commit capital.
Otherwise, there is a risk of investing in additional equipment that merely moves the bottleneck somewhere else in the factory, which is a rather expensive way of discovering that production is a system rather than a collection of machines.
I work with business owners, directors and investors to assess operations, technology and business processes, identify constraints and evaluate improvement and investment opportunities.
In manufacturing, this means looking beyond individual machines to understand how the factory actually operates, where productive capacity is being lost and whether process improvements, automation or additional capital expenditure offer the strongest commercial return.
Is the capacity already on your floor? Considering another machine, another shift or a factory improvement programme?
Start with the operation you already have!
Send me your production figures, shift logs, equipment quotation or a description of the capacity problem you are trying to solve.
I can help assess where the constraints are, which losses are worth investigating and whether recovering existing capacity makes more commercial sense than buying additional equipment.
And if the analysis shows that new equipment or technology is the right answer, at least you will know why you are buying it.